CHALLENGES & INNOVATIVE SOLUTIONS

CHALLENGE

Steep Embankment Construction within Constrained Right-of-Way

Elevating the road grading to reach the required bridge approach level over a public waterway at the Lampang bypass required significant earthworks. However, severe spatial limitations mandated the construction of unnaturally high-angle embankment slopes.

  • Restricted Right-of-Way: Limited spatial boundaries along the alignment prevented the use of standard, naturally stable slope gradients.

  • High-Angle Elevation: Reaching the necessary bridge clearance elevation within the confined area required the design of an aggressively steep earth embankment.

  • Waterway Adjacency Risks: Constructing massive earthworks immediately adjacent to a public waterway increased the critical need for immediate erosion control and structural stability.

  • Long-Term Facing Degradation: Utilizing temporary containment materials (like soil bags) presented a future risk of soil leakage and facing failure once the materials naturally decompose over time.

SOLUTION

Geosynthetic Reinforcement and Bio-Engineered Facing

To achieve the required elevation and ensure long-term stability within the spatial constraints, the engineering team implemented a Mechanically Stabilized Earth (MSE) wall utilizing geogrids and specialized creeping vegetation.

  • Geosynthetic Reinforcement: Integrated high-strength geogrids to internally stabilize and reinforce the steepened soil mass.

  • Flexible Soil Bag Containment: Utilized a soil bag facing system in combination with the geogrids to efficiently construct and shape the high-angle embankment face.

  • Bio-Engineered Surface Protection: Planted Singapore Daisy, a robust creeper plant, directly into the facing to establish a dense, living vegetative cover.

  • Decomposition Mitigation: The creeping vegetation was strategically selected to interlock and form a permanent protective bio-layer, effectively preventing soil leakage as the temporary soil bags naturally degrade.

THE OUTCOME

Sustainable and Stable High-Angle Embankment

The engineering team successfully constructed the steep road embankment within the limited ROW, safely achieving the necessary bridge approach elevation. The integration of the geogrid-reinforced soil bag system provided immediate structural stability, while the Singapore Daisy successfully matured into a dense, fully functional vegetative facing. This bio-engineered solution effectively extended the lifespan of the MSE wall, ensuring long-term soil containment and structural integrity without compromising the adjacent public waterway.

Green

Structure

Stable

Steep slope

Quick

Construction

S__9003025.jpg

PROJECT DOCUMENTATION

Discuss Your Infrastructure Needs

Partner with Lanna Geotech for technical precision and resilient geohazard mitigation. Our expert team is ready to support your engineering requirements from survey to project completion.

bottom of page